Get an environmental permit from NEPA

Large or risky projects need a NEPA permit before work starts.

⚠ The main official link is not working right now. Try again later, or use the office option below.
Apply online (JDAP)

Opens the official government site.

Who can do this

Anyone planning a listed project, for example: 10 or more lots or houses, hotels with 12+ rooms, clearing 10+ hectares, quarries, dredging, ports and marinas, or filling or clearing wetlands, mangroves or beaches.

What you need

Tick things off as you gather them.

Steps

  1. Check with NEPA whether your project needs a permit or licence.
  2. Register on JDAP and get a customer number.
  3. Click Apply for a Permit and choose Environmental Permit Application.
  4. Upload the PIF and documents, and pay online.
  5. NEPA tells you within about 15 working days if you need an EIA.
  6. Track it on JDAP. Pay the permit fee and collect the permit.
  7. Don’t start work before you have it. You can be fined or jailed.

Cost

Housing, subdivisions, hotels, mining and site clearing: $85,000 application + $40,000 permit. Most others: $50,000 + $40,000. Confirm with NEPA.

How long

About 15 working days to hear if an EIA is needed.

Can’t go online?

NEPA Westmoreland, Marine Park Building, Norman Manley Blvd, Negril: 876-957-3891. Montego Bay, RADA Complex, Catherine Hall: 876-971-0612. Head office, Kingston: 876-754-7540 or 1-888-991-5005.